Decide Fast & Get 50% Flat Discount | Limited Time Offer - Ends In 0d 00h 00m 00s Coupon code: SAVE50

Master PMI PgMP Exam with Reliable Practice Questions

Page: 1 out of Viewing questions 1-5 out of 453 questions
Last exam update: Nov 09,2024
Upgrade to Premium
Question 1

Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week.

What must the new program manager do before program closure?


Correct : D


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

A company's marketing department fails an internal compliance audit. To comply with the auditor's remediation plan, the legal department mandates that a content management system (CMS) be implemented. After initiating the program for CMS implementation, the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.

What should the program manager do to ensure the success of the program?


Correct : B


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

The program selection committee presents several programs for approval:

Program A is estimated to cost US$250,000, and has an annual cash inflow of US$75,000. Program B is estimated to cost US$150,000, and has an annual cash inflow of US$55,000. Program C is estimated to cost US$100,000, and has an annual cash inflow of US$45,000. Program D is estimated to cost US$200,000, and has an annual cash inflow of US$35,000.

Which program was selected based solely on a three-year return on investment?


Correct : C


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.

What should the program manager do next?


Correct : A


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required.

What should the program manager do next?


Correct : B


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500