Question 1

A manufacturing company uses discreet manufacturing to make skateboards. Production order picking lists are manually posted after finished good are reported as finished.

A production order has six picking lists posted. The quantities on the picking lists do not match any of the reported or finished quantities. This causes an inventory error for the raw materials. All taw material transactions must be tracked on production order and reconciled.

You need to process a single picking list for each production order.

What should you do first?


Correct : C


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.

An employee discovers an error after a time and attendance record is approved and transferred. The payroll transfer has not been run. However, the time has been posted against the production order.

You need to reverse the transferred registrations.

What happens to the production order time posting?


Correct : B


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

A manufacturer uses discreet orders and manually consumes raw material after reporting products as finished.

You are performing an end-of-month closing for remaining picking lists on production orders. You must not be required to consume the full amount of material on production order picking lists as a result of improved production efficiency. When the production manager verifies that no material is left to consume, there are remaining back-ordered amounts.

You need to pick the line item short and eliminate the remaining demand.

What should you do?


Correct : A


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

A customer produces light projection toys for holiday decorations throughout the year.

You are in the first month of a season. Production flows take one day to complete.

The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs.

You need to plan the jobs to be completed two weeks prior to the start of the next season.

What are two possible ways to achieve this goal? Each correct answer presents a complete solution.

NOTE; Each correct selection is worth one point.


Correct : B, F


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

You are responsible for product and formula maintenance for a paint manufacturer. You create a formula for white paint and add its lines. When the formula size increases or an ingredient changes, the quantity of the pigment ingredient must be adjusted proportionately. You need to set up the formula line for the pigment. Which formula feature should you use?


Correct : C


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500