As the Test Manager for an agile project how would you BEST plan and guide the testing activities during development? SELECT ONE OPTION
Correct : B
Start a Discussions
Which of the following statements correctly describes a 'depth-first approach' to managing risk based testing? SELECT ONE OPTION
Correct : A
Start a Discussions
Which one of the following options would help ensure success in using an Exploratory Testing approach? SELECT ONE OPTION
Correct : D
Start a Discussions
Club 65 to 90 is a holiday club for retired people run by a small company, the IT department consists of 1 Designer, 3 Developers and 1 System Tester Their booking system has been "live" for a number of years and the company has a loyal client base. A variety of automation tools are used for development and testing to improve effectiveness and efficiency.
A new project will introduce a loyalty scheme and both a Business Requirement Specification and a System Design Specification have been produced A Rapid Application Development (RAD) lifecycle model will be used where time is crucial. In the past there have been problems with updates to the existing system, which has affected existing functionality. Testers have not used representative and realistic operational profiles and data, which has led to significant production problems. The following test policy statements have been proposed for the project:
a. Testing must be risk based;
b. A Master Test Plan, confirming to IEEE829, must be produced for each test project;
c. Test procedures must be run by a tester who did not write the procedure;
d. Regression testing should be carried out on all releases;
e. The testers are accountable for all defects found in production;
f. Time must be given to designing test environments so that they are representative of the live environment. Which of the following options identifies the three policy statements that would be MOST beneficial for this project?
Correct : C
Start a Discussions
Which one of the following metrics would be MOST suitable for helping to determine whether test analysis and design is complete? SELECT ONE OPTION
Correct : D