An enhancement project does not change the functional sizing of the application, but just the GSCs. The application's aAFP was 101 FPs, with a VAF of 1.01. The following generic system characteristics are changed as described: a) Flexible query and report facility was provided that can handle simple requests; now this facility can handle complex requests b) Business control data was kept in tables that are maintained by the user with on-line interactive processes, but changes take effect only on the next business cycle; now changes can take effect immediately What is the aAFPA?
Correct : C
Start a Discussions
A new development project contains 3 GSC valued at 3 DI, 4 valued at 4 DI, 4 valued at 0 DI and 3 valued at 2 DI. What is the TDI?
Correct : C
Start a Discussions
An enhancement project added 3 high complexity EIs, changed 1 EI from average to low complexity and deleted 3 low complexity EIs. What is the EI contribution to enhancement function point measure?
Correct : A
Start a Discussions
An enhancement involves changing an EQ with 12 fields to include 3 extra fields. The EQ referenced 3 files before the change, and one extra file needs to be referred to as part of the change. How would the enhanced EQ be counted?
Correct : D
Start a Discussions
An application has 3 ILFs and 3 EIFs, all of average complexity. An enhancement to the system creates a new query with 22 attributes that displays data from each of the existing ILFs and EIFs. The new query also updates one of the existing ILFs. The original application FP was 200. What is the new AFPA?
Correct : B