Question 1

A user wishes to perform the same work tasks on several assets simultaneously. How can this be configured?


Correct : A

To perform the same work tasks on several assets simultaneously, a route can be created in the Routes application. A route is a series of work orders that are generated in a specific sequence to maintain a group of assets. Each stop in the route can be associated with a specific asset, and the job plan can be assigned to the route record, which means the same job plan tasks can be performed on each asset.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

At which data storage level are locations, assets and storerooms defined?


Correct : B

Locations, assets and storerooms are defined at the Site level in IBM Maximo Manage.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

Which statement is true regarding Work Assets in the Safety Plans application?


Correct : B

In the Safety Plans application, a Work Asset is either a location or an asset that requires the safety plan. Each safety plan record must have at least one work asset specified, and the work asset can be a location or an asset.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

At what database level does a Job Plan exist?


Correct : C

A Job Plan exists at the SITE level in IBM Maximo Manage.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

Which two statuses of a Purchase Order will allow a receipt of new items to be processed in the Receiving application if the Purchase Order is not being revised?


Correct : A, C

In IBM Maximo Manage, if a Purchase Order is not being revised, two statuses that will allow a receipt of new items to be processed in the Receiving application are APPR and INPRG.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer: