Question 1

A project manager provided details regarding the completion of the following tasks:

Equipment procurement took less time than estimated.

Equipment installation went according to schedule.

Which of the following should the project manager update?


Correct : B

The Project Gantt chart is a scheduling tool used to track task progress and timelines. When tasks are completed ahead of schedule, updating the Gantt chart ensures accurate tracking. This aligns with CompTIA Project+ recommendations on project scheduling and monitoring.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?


Correct : A

Forcing is a conflict resolution technique where the project manager makes a decision unilaterally, without seeking consensus. According to CompTIA Project+, forcing may be used when time is critical, and decisions need to be made promptly.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?


Correct : B

A decision tree helps in evaluating various choices and their potential outcomes, making it suitable for comparing vendors based on costs and risks. This aligns with CompTIA Project+ methodologies for decision-making tools and analysis.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?


Correct : D

A defect log tracks and details all bugs and issues identified in a project. This log is essential for quality control and continuous improvement, as recommended by CompTIA Project+ guidelines on project monitoring and control.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?


Correct : B

Applying the contingency plan is the immediate response to mitigate a security risk. CompTIA Project+ emphasizes the importance of having pre-established contingency plans to handle potential risks promptly and effectively.