Refer to the exhibit.
Refer to the exhibit. The monitoring team reports an inability to access the devices after a new centralized management integration. Which action resolves the issue?
Correct : C
Start a Discussions
Refer to the exhibit.
Refer to the exhibit. UCS- 1 fails to connect to the storage array. Which action resolves the issue?
Correct : B
Start a Discussions
A Cisco uCs C-Series Server powers off due to a power outage. The server should turn on when the power is restored with a fixed delay of 3 minutes. However, it remained powered off for more than 3 minutes after the engineer powered it back online. Which two actions resolve the issue (Choose two.)
Correct : A, C
Start a Discussions
Refer to the exhibit.
Refer to the exhibit. To avoid service disruption, an engineer must move the_ server from LEAF_ 1 to LEAF_ _2. After running the test, the engineer noticed that L EAF_ 2 failed to forward network traffic into the VXL AN fabric. The BGP, interface NVE, and VNI were confirmed to be configured as expected. Which two actions must be taken on L EAF_ 2 to resolve the issue? (Choose two.)
Correct : A, E
Start a Discussions
Refer to the exhibit.
A network engineer is implementing an RBAC on the Cisco Nexus 9000 Series Switch. The role called Host A fails to clear LACP counters on the port channel 20. Which configuration resolves the issue?
Correct : B
Start a Discussions