Which two options are available with Workfront reports? (Choose two.)
Correct : B, C
In Adobe Workfront, Planned date-based calendar reports are commonly used to visualize project timelines, milestones, and deadlines. They help teams plan and manage workloads based on dates and other time-related factors.
Filters with custom grouping allow users to customize their reports by organizing data in a meaningful way, tailored to specific project or team requirements. Custom groupings enhance the clarity of reports by categorizing data based on selected criteria.
The other options are not correct because Workfront does not support reports that reference multi-select custom fields in a chart format, nor does it allow object names longer than 500 characters.
Start a Discussions
Refer to the exhibit.
Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?
Correct : A
In Adobe Workfront, and in general project management, the Critical Path refers to the sequence of tasks that directly impacts the project's overall timeline. Tasks on the critical path are marked in red on a Gantt chart to indicate that any delay or change to these tasks will affect the entire project's completion date. These tasks are essential for maintaining the project schedule and ensuring timely delivery. Baselines are used for comparison against the current progress, and Milestones mark significant checkpoints but do not necessarily affect the project timeline if they are delayed.
Start a Discussions
Which field is used to create a milestone step on a milestone path in the Setup area?
Correct : C
In Adobe Workfront, when creating a Milestone Step within the Setup area, the Key field is essential as it serves as a unique identifier for each milestone step. It is used to define the specific step within a milestone path that can be associated with tasks in a project. The Status and Description fields are not used for creating the milestone step itself but are more relevant for defining attributes or metadata.
Start a Discussions
A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?
Correct : C
Even though tasks may be marked as 100% complete, their Status may still be listed as incomplete in reports if the task's status has not been updated to 'Completed.' The Status column provides insight into the current state of the task, which helps identify if the task is still listed as 'In Progress' or another incomplete status despite being marked as fully complete. Adding this column clarifies why the task appears in the Incomplete Tasks Report.
Start a Discussions
A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?
Correct : A
The best approach is to generate a Project Report in Workfront, where the report filters the Actual Completion Date for the past year and groups projects by the Sponsor and the month of completion. This allows the sponsor to see exactly which projects they sponsored and when they were completed within the selected timeframe. Grouping by month provides a clear visual of the completion timeline.
Start a Discussions